Summer 2019 Improvements to Our Church
Two summer construction projects are scheduled to enhance our church building and exterior. Read more below, and keep us in prayer during this time of transition!
Roof Replacement Project
The twenty-three-year-old roof over the Sanctuary and Office area will be replaced, due to wind and rain damage. This project emerged as an urgent need after the winter. The replacement will commence July 8, and last approximately 6 weeks.
Concrete Project
Following the roof replacement project, our concrete project will start on August 19. The project will consist of replacing the retaining wall at the north end of the church, and the stairs from the patio down to the east end of the Kensington Nursery School walkway, as well and the patio itself and the wooden deck leading to it from the church Social Hall. This project is expected to last 4-6 weeks.